Karl Scotland – Using Agile to Deliver Value
Archive for February, 2012
Kanban Thinking on SPaMCAST
Feb 20th
I recently gave an interview with Tom Cagley who puts together the Software Process and Measurement Cast, and talked about what I am calling Kanban Thinking. The result has just been published – have a listen and let me know what you think.
The Science of Kanban – Conclusions
Feb 3rd
This is the final part of a write-up of a talk I gave at a number of conferences last year. The previous post was about the science of economics
Scientific Management Revisited
Is scientific management still relevant for product development then? As I have already said, I believe it is, with the following clarifications. I am making a distinction between scientific management and Taylorism. Whereas scientific management is the general application of scientific approach to improving processes, Taylorism was his specific application to the manufacturing domain. Further, in more complex domains such as software and systems development, a key difference in application is that the workers, rather than the managers, should be the scientists, being closer to the details of the work.
Run Experiments
The used of a scientific approach in a complex domain requires running lots of experiments. The most well-known version is PDCA (“Plan, Do, Check, Act”) popularised by Deming and originally described by Shewhart. Another variation is “Check, Plan, Do”, promoted by John Seddon as more applicable to knowledge work because an understanding of the current situation is a better starting point, and Act is redundant because experiments are not run in isolation. John Boyd’s OODA loop takes the idea further by focussing even more on the present, and less on the past. Finally, Dave Snowden suggests “Safe To Fail” experiments as ways of probing a complex situation to understand how to evolve.
Whichever form of experiment is run, it is important to be able to measure the results, or impact, in order to know whether to continue and amplify the changes, or cease and dampen them. The key to a successful experiment is whether it completes and provides learning, not whether the results are the ones that were anticipated.
Start with Why
Knowing whether the results of an experiment are desirable means knowing what the desired impact, or outcome might be. One model to understand this is the Golden Circle, by Simon Sinek. The Golden Circle suggests starting with WHY you want to do something, then understanding HOW to go about achieving, and then deciding WHAT to do.
Axes of Improvement
One set of generalisations about WHY to implement Kanban, which can inform experiments and provide a basis for scientific management is the following:
- Productivity – how much value for money is being generated
- Predictability – how reliable are forecasts
- Responsiveness – how quickly can requests be delivered
- Quality – how good is the work
- Customer Satisfaction – how happy are customers
- Employee Satisfaction – how happy are employees
The common theme across these measures is that they relate to outcome or impact, rather than output or activity. Science helps inform how we might influence these measures, and what levers we might adjust in order to do so.
Lean
In these posts I have described Kanban in terms of the sciences of people, process and economics. However, this can actually be generalised to describe Lean as applied to knowledge work, as opposed to the traditional definition of Toyata’s manufacturing principles. The differentiation is also a close match back to my original Kanban, Flow and Cadence triad.
- Kanban maps to process, with the emphasis on eliminating delays and creating flow rather than eliminating waste.
- Flow maps to economics, with the emphasis on maximising customer value rather than reducing cost.
- Cadence loosely maps people and their capability, with the emphasis on investing in those who use the tools rather than the tools themselves.
References
The ideas in this article have been inspired by the following references:
The Science of Kanban – Economics
Feb 2nd
This is the fourth part of a write-up of a talk I gave at a number of conferences last year. The previous post was about the science of process
Having a good understanding of how creative people can have an efficient process still isn’t enough however. As Russell Ackoff is often quoted as saying, “It’s better to do the right thing wrong, than the wrong thing right”. An understanding of economics is needed to avoid “doing the wrong thing right”, by focussing on the “right thing”, whether that involves financial return, risk management or information discovery, all of which are of value. One financial model that I picked up from Chris Matts is that features should increase future revenue, protect existing revenue, reduce existing costs, or avoid future costs.
Life Cycle Profits
A basic understanding of investment over time helps explain why smaller batches and smaller increments are preferable from an economic perspective. In Software by Numbers, Denne and Cleland-Huang show the investment, payback and profit periods. A smaller cash injection, over a shorter investment period, can enable a product to become self-funding and break-even sooner, such that the profit can be invested back into the product for continued development.
Cost of Delay
The Cost of Delay concept, as popularised by David Anderson, further informs scheduling decisions based on cost over time. The four most common archetypes used (but limited to) are:
- Expedite – the cost of delay is high and immediate. These items are genuinely urgent and should be prioritised above everything else.
- Standard – the cost of delay rises linearly. Examples are items with an opportunity cost, where the later the delivery, the more opportunity for gain is lost.
- Fixed Date – the cost of delay rises sharply at a specific date. Examples are regulatory dates at which fines may be imposed, or seasonal dates such as Christmas or trade-shows.
- Intangible – the cost of delay is likely to happen in future, but the exact nature is unpredictable. Examples are technical debt or infrastructure work
Information Theory
Value does not have to be purely financial. In particular there is often value in information generated, as suggested by information theory.
Information Theory says that for experiments with pass/fail results, a 50% failure rate is optimal. Always failing suggests that nothing is known, and subsequently nothing is being learned. Always succeeding suggests that everything is already known, and thus nothing is being learned.
The Lean Startup approach is essentially based on information theory, with the goal being to loop through the Build, Measure and Learn cycle as quickly as possible.
This can be thought of as buying information, and asymmetric payoff curves help explain the benefits of this approach. Given some notional performance target, an asymmetric payoff curve is one where being below target results in a loss, being above target results in a gain, and hitting the target results in breaking even. Buying information enables the shape of the curve to be changed such that losses below target are minimised, and gains above target are maximised.
Scheduling
Having a good understanding of the economics enables better decision making when designing and scheduling the work. Usually selection of what work should be pulled next relates to cost and value. Higher value for lower cost generally trumps lower value for highest cost.
An example is risk reduction. There is value in risk reduction, where the higher the risk, the greater the value there is in reducing it, and there is also a cost associated with reducing the risk. Having an understanding of the relative values and costs of risk reduction activities informs the sequencing of high value, low cost items earlier and low value, high cost items later.
Similarly Set Based Concurrent Engineering can be informed by economics. SBCE involves working on multiple parallel initiatives in order to reduce risk. Multiple initiatives should only be run while the total cost of the initiatives is less than the value of the risk reduction. Each additional initiative adds less value exponentially, while the total cost rises linearly. Multiple experiments are like buying insurance; when the cost of the insurance is greater than the economic benefit, it’s not worth paying for.
In the final part, I’ll draw together some conclusions.
The Science of Kanban – Process
Feb 1st
This is the third part of a write-up of a talk I gave at a number of conferences last year. The previous post was about the science of people.
Even though a kanban system describes knowledge work, we can still apply formal sciences such as mathematics. Rather than applying them at a detailed, micro level, we can take a system approach and apply them at the broader, macro level. As an example, if we try and predict the result of a single coin toss, we are only able to do so with 50% accuracy due to the unpredictable, random nature. However, if we to try to predict the result of 1000 coin tosses, we can be more accurate, albeit with less precision and some degree of variance.
Queuing Capacity Utilisation
The most common mathematics used with kanban systems is associated with queues and utilisation. Queuing capacity utilisation suggests that as capacity utilisation increases, queues increase exponentially. Thus extremely high utilisation will result in large queues.
Further, Little’s Law tells us that the time something is in a queue (lead time) is equal to the size of the queue divided by the processing rate.
Lead Time = WIP / Processing Rate
It follows then, that if we want to complete work quickly (i.e. with a short lead time), then should reduce queues, which requires reducing utilisation. Reducing utilisation too much, however, will begin to have diminishing returns.
Traffic Flow Theory
Traffic Flow Theory gives an explanation as to why a work-in-process limit on one may be too low.
Originally observed by Bruce Greenshields in 1934, Traffic Flow Theory describes how, as speed (in miles per hour) goes up, the density of traffic (in vehicles per mile) goes down, and vice versa. This is observable on roads with a low density of cars (i.e. empty) which are able to travel at high speeds, and roads with a high density of cars (i.e. gridlocked and bumper to bumper) which are stationary. Flow is defined as the product of speed and density, and thus there is an inverse u-curve, with high flow in the middle, and low flow at either end due to either low speed, or low density.
For product development, density can be viewed as work in process, speed correlates to lead time, and flow correlates to throughput. If work in process is too low for the available capacity, then lead time will be short, but throughput will be low. Similarly, if work in process is too high for the available capacity, then lead time will be long, and throughput will be low.
An interesting effect happens on either side of the flow curve.
On the left side, if density is increased (increasing work in process), speed decreases (increasing lead time), and flow decreases (decreasing throughput). The decreased flow causes a further increase in density resulting in a negative reinforcing loop.
However, on the right side, if density is increased (increasing work in process), speed decreases (increasing lead time), and flow now increases (increasing throughput). The increased flow causes a decrease in density resulting in a balancing loop.
Thus, while the optimum density is unlikely to be achieved precisely, it is better to be on the right hand side, with slightly less work in process, where a slight increase will balance itself out.
Feedback
It’s generally recognised that software development is a non-linear activity, due to the many feedback loops, so it’s useful to understand the effect that the feedback loops have on a process.
One of the impacts that a feedback loop has is related to its delay, where a long delay can lead to instability and oscillation. Taking a shower as an example, if when trying to turn the heat of the shower up, there is a long delay between turning the tap and the water temperature increasing, the natural reaction is to turn the temperature tap further. Eventually, when the change in water temperature comes through it will be too hot. The same can happen again when trying to turn the heat of the shower down again.
Thus it is a good idea to minimise delays in feedback, or put another way, have fast feedback. Fast feedback also results in smaller queues, because less work builds up waiting for feedback. Smaller queues result in less work in process, and we have seen that lower work in process leads to shorter lead times. Shorter lead times further generate faster feedback, resulting in a positive reinforcing loop.
In the next part we’ll cover the science of economics.